Topregal expanding Pasewalk site
Topregal has completed two new 5,000 m² production and storage halls at its Pasewalk site ahead of schedule.
The two warehouses complement four already existing halls on total area of 82,000 m². As Topregal reported, at least 20 new jobs will be created. Initially the object was due to be finished in the second half of 2025. “We’re delighted that they’ve now been completed earlier,” said Jürgen Effner, managing director of Topregal.
Each new hall features rooftop photovoltaic systems with 550 kWp capacity. The system on hall 1 already supplies power for production use. Once all six rooftops are connected, the 2,800 kWp output will be partially fed into the regional grid.
“We’re excited to grow our Pasewalk operations faster than expected and are continuing to invest in sustainable production,” says managing director Effner. (js)